Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner.

Standardisation would help sustainability – RWE

Topsides UK
BIG LIFT: The topsides of BP’s Andrew platform being lowered into place. This was a classic CRINE era project where capital cost reduction was pursued ruthlessly

RWE Dea’s gas production boss has called for a return to the CRINE cost-cutting principles of the 1990s after facing major project delays and cost increases.

Paul Jeffs, head of production and exploration at RWE Dea UK, outlined a series of delays, rig availability issues and cost overruns on the firm’s Breagh and Clipper South projects in the southern North Sea (SNS).

Recent figures released by its partner on Breagh, Sterling Resources (30% owner) showed costs had gone up 17% on the project, from £485million to £566million.

This, it said, was due to a delayed start on pipeline installation and harder-than-expected trenching conditions. Development drilling costs had also added to the cost increase and onshore plant equipment had been damaged during shipping.

RWE also had issues agreeing onshore pipeline routes, said Jeffs, speaking at the 2012 Southern North Sea Conference, run by EEEGr, having to deal with 22 land owners and having to replant 22 different types of grass in one area.

He said there were also increasing contractual difficulties. Simplicity brought in under the 1990s CRINE (Cost Reduction Initiative for the New Era) initiative had now been eroded and contracts were now becoming increasingly adversarial, he said.

These issues were making business in the basin unattractive when compared to 30trillion cu.ft gas finds off Mozambique, he added.

“Cost overruns and lateness undermine our product,” he said. “Costs of gas fields are growing to a level where the southern North Sea is becoming unattractive.

“Let’s bring back some standardisation initiatives to get come costs under control. We are squabbling over slices of the cake when the whole cake is shrinking. We should be looking at the whole cake not our own sales.”

He said costs on one contract had risen 27%, with additional costs rising 46% on top of that.

However, the CRINE initiative, which focussed on cutting capital costs, has had its critics, with complaints that the cost-cutting has led to later life issues with infrastructure.

Other issues facing operators were delays on drilling due to rigs being delayed on previous projects and general tightness in the rig market.

“You can’t get a rig,” said Jeffs. “There are none available until 2014. They have gone to other markets. That delay affects our business. It affects our sustainability.”

Last year, the firm installed platforms on its operated Clipper South and Breagh fields, both due on stream from summer.

Drilling started in February on Clipper South, which has 500billion cu.ft in place, and it is due to start on Breagh as part of the first phase of development.

RWE has also faced delays on Clipper South, where it is drilling three 1,600m (5,000ft) long horizontal wells and using multi-fracturing to access tight gas in low permeability rock.

The project was also delayed – six months – due to pipelaying being behind and the rig was three months late.