Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner.

MPs call for explanation of further delay on Hinkley Point nuclear power station

Computer generated image issued by EDF of the planned  Hinkley  Point C nuclear plant, agreed with the UK Government.
Computer generated image issued by EDF of the planned Hinkley Point C nuclear plant, agreed with the UK Government.

Officials from energy giant EDF are being called back to Parliament to explain to MPs a further delay in the Hinkley Point nuclear power station.

The Energy and Climate Change Committee said it wanted to question senior representatives from the French firm about the long-awaited final investment decision on the £18 billion project.

Chief executive Vincent de Rivaz told the committee last month that Hinkley Point would definitely go ahead, pointing to a speech by French economy minister Emmanuel Macron that the final investment decision will be made in early May.

But Mr Macron said at the weekend that the green light may not be given until September.

Angus MacNeil, chairman of the Energy and Climate Change Committee, said: “When EDF appeared before us in March, company bosses were insisting that a decision would be made in May.

“At that hearing we said that we would call them back in if that timetable slipped again and that’s what we are doing now.

“If Hinkley does not go ahead it could have huge implications for our future energy security and efforts to cut climate-changing emissions.

“We will therefore be watching progress on this closely. If we have to see EDF back here in September as well, we will.”

Dates and times for the hearing will be confirmed in due course, but it is expected to take place in late May.

Mr de Rivaz told MPs in March that the project had successfully passed regulatory, political, commercial and operational milestones.

EDF had invested £2.4 billion in the project and continued to spend £55 million a month, he said.

Asked about a date for the long-awaited final investment decision, he said it would be “soon”.