Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner.

River Don Crossing to be ‘finished by Christmas’

Aerial Photographs 
Aberdeen Western Peripheral Route / AWPR
Pictured is the Northern Route between Dyce / Aberdeen Airport and Blackdog. Pictured is the new bridge at Dyce over the River Don which is still under construction.
Picture by DARRELL BENNS   
Pictured on 06/10/2018 
MUST CREDIT - CABRO AVIATION and HJS HELICOPTERS
Aerial Photographs Aberdeen Western Peripheral Route / AWPR Pictured is the Northern Route between Dyce / Aberdeen Airport and Blackdog. Pictured is the new bridge at Dyce over the River Don which is still under construction. Picture by DARRELL BENNS Pictured on 06/10/2018 MUST CREDIT - CABRO AVIATION and HJS HELICOPTERS

The Aberdeen bypass contractors have said work on the River Don Crossing should be finished by Christmas subject to the weather and safety checks.

A document submitted to the Scottish Parliament by Balfour Beatty and Galliford Try has said completion of the crossing would allow for the “opening of the full project”.

The paper was lodged with Holyrood ahead of a committee meeting today where contractors will be grilled by MSPs amid mounting concern over the delays and costs to the Aberdeen Western Peripheral Route (AWPR).

MSPs are expected to tackle the contractors on the opening date for the £745 million road as well as demand answers on how much money has been spent on the project.

The document warns that the contractors will suffer “huge” losses even if they are successful in their compensation claim with Transport Scotland.

Last month there was anger when Transport Secretary Michael Matheson announced the AWPR completion date had been pushed back from “late autumn” to December.

The document states: “The remedial works (on the Don Crossing) are forecast to be complete just before Christmas, which would allow opening of the full project – albeit that is a challenging programme as the works are highly susceptible to adverse weather, and are subject to stringent safety tests.”

The contractors also noted the project was forecast to complete “approximately” 13 months late – a reference to an earlier ambition for the road to be open last winter.

The contractors are discussing compensation claims for cash outwith the £745m fixed-cost spent on the project with Transport Scotland.

“Even after resolution of the claim, the joint venture partners’ losses will be huge,” the document adds.

North East Tory MSP Peter Chapman said: “Motorists would be delighted if this road was open by Christmas – but I don’t think anyone is holding their breath.

“We need to know exactly how big these reported losses are. People also deserve to be told when they can finally drive on the road – as the transport secretary seems unwilling or unable to name a date.”