Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner.

Ørsted fully commissions Borssele 1 & 2 offshore wind farm in Dutch North Sea

© Supplied by OrstedBorssele 1 & 2 offshore wind farm
Borssele 1 & 2 offshore wind farm

Ørsted has fully commissioned its Borssele 1 & 2 offshore wind farm in the Dutch North Sea.

The 94-turbine development has a total capacity of 752 megawatts (MW), making it the second largest operating offshore wind farm in the world and the largest in the Netherlands.

Comprised of Siemens Gamesa 8 MW turbines, Borssele 1 & 2 are located around 14 miles off the coast of the province of Zeeland.

It will provide enough green energy to power one million Dutch households.

Henrik Poulsen, chief executive and president of Ørsted, said: “This is an important milestone for the green transformation and for Ørsted. We’re proud that we’ve commissioned our first offshore wind farm in the Netherlands, who is among the global frontrunners in the energy transition.

“With Borssele 1 & 2 as the first step, we wish to make a significant contribution to the Dutch transition from fossil to renewable energy. We’re proud that we completed this large-scale clean energy project on time and within budget during the COVID-19 pandemic, while maintaining our focus on health and safety.”

Steven Engels, general manager Benelux at Ørsted, said: “It’s great that we now can deliver enough green electricity to power one million Dutch households. Ørsted has delivered what it promised back in 2016, when we won the tender with a ground-breaking bid price.

“Realising the first project of the large-scale offshore wind roll out programme in the Netherlands is an important milestone for the Dutch energy transition.

“I’d like to thank the Dutch national and regional governments and so many other stakeholders who have helped us achieve this result. Zeeland has welcomed us with open arms, which provides an excellent starting point for our operations out of Vlissingen for many years to come.

“Moreover, it’s a good basis for future projects around industry decarbonization in the region, such as the renewable hydrogen project that we announced with Yara.”

Flemming Thomsen, Ørsted’s senior programme Ddrector for Borssele 1 & 2, added: “Together with our suppliers, our construction team has successfully installed this wind farm at high quality in less than nine months.

“By introducing additional health and safety measures offshore as well as onshore, we were able to continue construction during a global pandemic. We’re grateful and proud of the result delivered and pleased to witness the commissioning of Borssele 1 & 2.”