Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner.

Shetland to Caithness subsea electricity link given provisional approval

Sutherland windfarm

Plans for a subsea electricity cable linking Shetland to the mainland have been provisionally approved by the energy regulator.

Ofgem said it is minded to approve the Scottish and Southern Energy Networks (SSEN) 600MW transmission link, which would allow new wind farms on Shetland to export renewable electricity to the rest of the UK and help ensure security of supply on the islands.

However it said it is minded to reject a similar project in the Western Isles.

The Shetland project would consist of a single 600MW subsea circuit from Kergord on Shetland to Noss Head in Caithness on the Scottish mainland, connecting into SSEN’s recently completed Caithness-Moray transmission link.

It is estimated the link would cost around £709 million and would be completed in 2024.

Ofgem is now consulting on approving the link subject to SSEN demonstrating, by the end of 2019, that the Viking Energy Wind Farm project planned for Shetland has been awarded subsidies through the UK Government’s Contracts for Difference (CfD) auction.

Colin Nicol, managing director of SSEN, said: “Ofgem’s decision to provisionally approve SSEN’s 600MW proposed transmission link is an important milestone in connecting Shetland to the mainland electricity network and helping to unlock its significant renewables potential.

“There are still a number of steps to be taken before we can proceed with the transmission connection, in particular the requirement for renewable developments to secure CfD support in this year’s auction, and we will continue to engage with key stakeholders during this consultation period.

“We also await clarity from Ofgem on their assessment of our proposed whole system solution.

“This decision will be important in reducing costs for consumers and securing the best economic case for delivery of renewable development in Shetland and Scotland’s other island groups.”

However, the energy regulator has suggested changes to SSEN plans for the western isles.

In a statement, Ofgem said: “Ofgem is minded to reject SSEN’s separate proposal to build a 600MW transmission link to connect the Western Isles to the mainland based on two Lewis Wind

Power wind farm projects being awarded subsidies through the CfD auction because of the risk of consumers paying for a significantly underutilised link.

“Ofgem would instead support an alternative proposal that more appropriately protects consumers from the additional costs of funding a potentially significantly underutilised link.

“This could be either a 450MW or 600MW transmission link depending on any revised proposals SSEN put forward.”

An initial estimate for the 600MW link for the western isles put the cost around £663 million and a 450MW link at around £617 million.

SSEN is calling on Ofgem to reconsider its provisional decision and said that a 450MW link would be short sighted, limiting the potential for community schemes to benefit from renewables expansion.

Mr Nicol said: “Moving to a 450MW at this late stage also introduces risks and uncertainty which, in turn, could impact on the delivery of a transmission link to the Western Isles.”

Ofgem said it plans to reduce costs by seeking to replicate the outcomes of competition and is minded to use the ‘Competition Proxy’ model, setting the revenue that SSEN can earn from building and operating the links.