Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner.

Harbour reaches key milestone on Talbot subsea development

© Supplied by Harbour Energywindfall tax harbour energy
Habour Energy's Judy platform

Harbour Energy has submitted an environmental statement for its proposed Talbot subsea development, with a view to reaching first oil in Q3 2024.

Located block 30/13e of the North Sea, Talbot lies around 170 miles south east of Peterhead, and a few miles west of the UK/ Norway median line, in water depth of around 75m.

Recoverable reserves at the field are estimated at around 18.1 million barrels of oil equivalent (boe) of light oil with associated gas.

Harbour holds a 67% operated interest in the field via two subsidiaries of its prior incarnation, Chrysaor, while Eni holds the remaining 33% equity interest. It acquired the licence via its acquisition of ConocoPhillips’ North Sea assets in 2019.

According to its statement submitted on 26 May, the proposed plan for the field centres on a three-well subsea development tied back to the Harbour-operated Judy platform, around 10 miles to the northwest.

Production from Talbot will be routed back to the platform via a new subsea production flowline and umbilical carrying power, communications, hydraulic supply, methanol and chemicals. This will tie-in to the existing Joanne South 12” pipeline at a point upstream of the Judy platform which provides processing and conditioning of gas and condensates from other J-block fields (including Judy, Joanne, Jade and Jasmine).

© Supplied by Harbour Energy
Talbot subsea development plan.

Once processed, gas will be transported as part of a commingled stream via an export line to the CATS pipeline system, and then on to Teesside for processing.

Liquids will be sent via a 24” oil export line to the Norpipe liquids pipeline and on to the Norsea terminal, also at Teesside.

Oil production from the field is expected to begin at around 3,817 tonnes per day of oil, and 1.7 million cubic metres of gas, both declining with time. Overall field life Is estimated at a minimum 10 years, but will be aligned to the cessation of production at Judy, the statement adds.

Harbour’s provisional timeline suggests development drilling will begin from Q4 2022, though its project summary notes it could begin “potentially Q3”.

Subsea infrastructure and pipelines will then be laid through 2023 and 20244, with a view to first oil from Q3 2024.

Its summary suggests Harbour will maintain its accelerated timeline for the field, with appraisal drilling at the prospect having begun less than a year ago, and an additional horizontal sidetrack having been completed in October.

This week Fitch Ratings said Harbour was among a group of medium-sized companies most exposed to the UK government’s Energy Profits Levy, given that around 90% of its current production is located in the UK North Sea.

However the ratings agency said the company has “sufficient headroom” to absorb the levy – not to mention the potential rebates offered should it proceed with investments in UK projects such as Talbot.